BOMwiki the bill-of-materials encyclopedia
30,454,201 parts mapped · 193,225 items
Discussion History

LNG Carrier

Product

Overview

A modern 174,000 m³ membrane LNG carrier is among the most part-dense ships afloat: shipbuilders describe the complete vessel as roughly 1.2 million discrete parts. The unusual share sits in the cargo containment. Where a crude tanker's tanks are bare steel, each of the four Mark III Cargo Tanks here is lined with GTT's Mark III system, thousands of corrugated stainless sheets over thousands of insulation panels, each panel levelled, anchored and sealed individually, so a single tank carries close to 98,000 components before any cargo machinery is counted.

The ship exists to move natural gas as a liquid at −163 °C, 1/600th of its gaseous volume. Everything unusual about the design follows from that temperature: the flexible membrane that shrinks without cracking, the insulation that keeps daily boil-off near 0.085 %, and the dual-fuel engines that burn the boil-off instead of venting it.

Hull and construction

The hull is a conventional double-hull structure erected from about 90 Hull Grand Blocks, each a pre-outfitted grand block of up to ~300 t. A block is itself a few thousand parts: sixty-odd Hull Plates, hundreds of Hull Stiffeners and Structural Brackets, and, dominating the count, as in every large welded structure, around 5,800 tracked Weld Seams. Across 90 blocks the hull alone passes half a million parts. Penetrations for pipe and cable runs are individually detailed Penetration Piece pieces, since every hole in the inner hull borders the cargo insulation space.

Cargo containment

The Mark III system is the reason this article's part count has six digits. Each tank's inner hull is lined first with Insulation Panels, reinforced-polyurethane-foam and plywood sandwiches about 400 mm thick carrying the bonded Triplex secondary membrane, set on Wedge / Shims and epoxy beds that take up hull fabrication tolerance, and pulled down by Coupler Studs threaded onto studs welded to the inner hull. A single tank uses on the order of 60,000 studs and couplers and over 20,000 wedges and shims.

Over the panels goes the primary barrier: 1.2 mm Corrugated Membrane Sheet sheets of 304L stainless steel, pressed with two-way corrugations and lap-welded to Anchoring Strips. The corrugations act as expansion joints, flexing as the membrane contracts several centimetres per tank length on cooldown. The membrane carries no structural load; cargo weight passes through the insulation into the ship's structure.

Each tank is served from a single Cargo Pump Tower hung from the liquid dome, a tripod of stainless Tower Pipe Sections carrying two main Submerged Cargo Pumps and a Spray / Stripping Pump to the tank floor, braced by Tower Clamps against sloshing loads. There are no other tank penetrations below the dome.

Cargo handling

The Cargo Handling Plant loads and discharges 174,000 m³ in around 12–14 hours through the port and starboard Cargo Manifolds. Boil-off gas is drawn off by four Boil-Off Gas Compressors, two high-duty for cargo operations, two low-duty feeding the engines, with Cargo Heaters warming vapour for tank gas-up and warm-up. Surplus boil-off can be recondensed and returned to the tanks by a Reliquefaction Unit, and an Emergency Shutdown System can halt transfer in seconds. The deck lines run through roughly 850 Cryogenic Valves and 2,400 insulated Pipe Spools on 3,800 Cryogenic Pipe Supports, joined by some 17,000 Flange Bolt Set Items.

Propulsion

Two 5-cylinder Dual-Fuel Two-Stroke Engines of the ME-GI type drive twin Fixed-Pitch Propellers through short Propeller Shaft Section lines in a twin-skeg afterbody. Each engine delivers about 12.4 MW at 66 rpm, injecting natural gas at 300 bar with a small pilot-oil charge; a low-speed engine of this bore is a several-thousand-part machine built up from five Cylinder Units on a Engine Bedplate, a Crankshaft clamped by Engine Tie Rods, twin Turbochargers and the double-walled Double-Wall Gas Pipe runs of its gas-injection system. Three High-Pressure LNG Pumps raise LNG to injection pressure, each engine takes gas through its own Gas Valve Unit, and a Gas Combustion Unit burns whatever boil-off the plant cannot use, keeping tank pressure in band without venting methane.

Ship systems

Electrical power comes from four dual-fuel Dual-Fuel Generator Sets feeding 6.6 kV Main Switchboards. The installation runs about 450 km of cable in 17,000 Cable Runs, restrained by 26,000 Cable Cleats and terminated through 9,000 Connectors, cabling alone is a five-figure part population. The Ballast & Machinery Piping group adds 6,000 Pipe Spools and 18,000 Flange Bolt Set Items across ballast, cooling and fuel systems, with three 3,000 m³/h Ballast Pumps managing the 50,000-odd tonnes of ballast water a light passage requires.

The crew of about 30 lives in the aft Deckhouse & Accommodation, outfitted from 38 prefabricated Cabin Modules and held together by some 29,000 Joiner Screw / Pins and pins. On deck, six Mooring Winches with 64 t brake loads hold the ship at the terminal while the manifolds are connected, and two enclosed Enclosed Lifeboats cover the full complement.

LNG Carrier parts and their functions

8 top-level parts · 1,158,280 parts in total · full bill of materials below
LNG Carrier parts diagram: 1 hull grand block, 2 mark III cargo tank, 3 cargo handling plant, 4 dual-fuel propulsion plant, 5 deckhouse & accommodation, 6 electrical system, 7 ballast & machinery piping, 8 deck machinery & lifesaving. 1,158,280 parts in 8 top-level items.
LNG Carrier parts diagram. Numbers match the table below; each box is one top-level part or assembly with what it contains.
#PartQtyWhat it does
1 Hull Grand Block 5 parts 90× Grand blocks erected in dry dock
2 Mark III Cargo Tank 7 parts 4× Mark III membrane tanks, ~100,000 parts each
3 Cargo Handling Plant 9 parts 1× Compressors, manifolds, cryogenic piping
4 Dual-Fuel Propulsion Plant 10 parts 1× Dual-fuel two-stroke plant
5 Deckhouse & Accommodation 4 parts 1× Accommodation and bridge
6 Electrical System 6 parts 1× ~450 km of cable
7 Ballast & Machinery Piping 5 parts 1× Ballast and machinery piping
8 Deck Machinery & Lifesaving 8 parts 1× Mooring, lifesaving

3D model

No 3D model yet. Have a CAD file of this? Add a 3D model. STL renders right on this page; STEP, FreeCAD, and OpenSCAD sources are welcome too (openly licensed, like all 3D models on BOMwiki).

Build & assembly graph

expand / collapse · shared sub-assemblies converge · links to related products · est. labour
product / assembly shared across products atomic part related product

Tap an assembly to expand/collapse · tap a part to open it · use “Open page” for any node · drag to pan, scroll to zoom.

Bill of materials for LNG Carrier

8 top-level lines · 122 rows shown · 1,158,280 parts total · indented to 3 levels
# Item / sub-assembly Part no. Qty/assy Ext. qty Parts Type
1 Hull Grand Block 5 parts lng-hull-block 90× 90 6,604 assembly
1.1 Hull Plate lng-shell-plate 60× 5,400 · part
1.2 Hull Stiffener lng-stiffener 274× 24,660 · part
1.3 Structural Bracket lng-bracket 420× 37,800 · part
1.4 Weld Seam lng-weld-seam 5800× 522,000 · part
1.5 Penetration Piece lng-pipe-penetration 50× 4,500 · part
2 Mark III Cargo Tank 7 parts lng-cargo-tank 4× 4 97,519 assembly
2.1 Corrugated Membrane Sheet lng-membrane-panel 1380× 5,520 · part
2.2 Insulation Panel lng-insulation-panel 5300× 21,200 · part
2.3 Anchoring Strip lng-anchoring-strip 2200× 8,800 · part
2.4 Coupler Stud lng-coupler-stud 62000× 248,000 · part
2.5 Wedge / Shim lng-wedge-shim 24000× 96,000 · part
2.6 Cargo Pump Tower 7 parts lng-pump-tower 1× 4 2,631 assembly
2.6.1 Submerged Cargo Pump 5 parts + deeper › lng-cargo-pump 2× 8 6 assembly
2.6.2 Spray / Stripping Pump 5 parts + deeper › lng-spray-pump 1× 4 6 assembly
2.6.3 Tower Pipe Section lng-tower-pipe-section 120× 480 · part
2.6.4 Tower Clamp lng-tower-clamp 90× 360 · part
2.6.5 Custody-Transfer Level Gauge lng-level-gauge 2× 8 · part
2.6.6 Emergency Pump Well lng-emergency-pump-well 1× 4 · part
2.6.7 Flange Bolt Set Item lng-flange-bolt 2400× 9,600 · part
2.7 Pressure Sensor pressure-sensor 8× 32 · part
3 Cargo Handling Plant 9 parts lng-cargo-plant 1× 1 27,094 assembly
3.1 Boil-Off Gas Compressor 6 parts lng-cargo-compressor 4× 4 9 assembly
3.1.1 Compressor Impeller lng-compressor-impeller 2× 8 · part
3.1.2 Compressor Casing lng-compressor-casing 1× 4 · part
3.1.3 Compressor Drive Motor lng-compressor-motor 1× 4 · part
3.1.4 Ball Bearing ball-bearing 2× 8 · part
3.1.5 Dry-Gas Seal lng-gas-seal 2× 8 · part
3.1.6 Fastener Set fastener-set 1× 4 · part
3.2 Cargo Heater lng-cargo-heater 2× 2 · part
3.3 Cargo Manifold 5 parts lng-cargo-manifold 2× 2 428 assembly
3.3.1 Manifold Spool lng-manifold-spool 8× 16 · part
3.3.2 Cryogenic Valve lng-cryo-valve 12× 24 · part
3.3.3 Drip Tray lng-drip-tray 2× 4 · part
3.3.4 Presentation Flange lng-presentation-flange 6× 12 · part
3.3.5 Flange Bolt Set Item lng-flange-bolt 400× 800 · part
3.4 Reliquefaction Unit 6 parts lng-reliquefaction-unit 1× 1 1,168 assembly
3.4.1 Cryogenic Heat Exchanger lng-cryo-heat-exchanger 3× 3 · part
3.4.2 Turbo-Expander/Compressor lng-expander-compressor 1× 1 · part
3.4.3 Cryogenic Valve lng-cryo-valve 40× 40 · part
3.4.4 Pipe Spool lng-pipe-spool 120× 120 · part
3.4.5 Control Cabinet 7 parts + deeper › lng-control-cabinet 1× 1 104 assembly
3.4.6 Flange Bolt Set Item lng-flange-bolt 900× 900 · part
3.5 Emergency Shutdown System 5 parts lng-esd-system 1× 1 982 assembly
3.5.1 ESD Valve 4 parts + deeper › lng-esd-valve 8× 8 4 assembly
3.5.2 ESD Initiator lng-esd-initiator 20× 20 · part
3.5.3 Hydraulic Power Unit 5 parts + deeper › lng-hydraulic-power-unit 1× 1 122 assembly
3.5.4 Control Cabinet 7 parts + deeper › lng-control-cabinet 2× 2 104 assembly
3.5.5 Cable Run lng-cable-run 600× 600 · part
3.6 Cryogenic Valve lng-cryo-valve 850× 850 · part
3.7 Pipe Spool lng-pipe-spool 2400× 2,400 · part
3.8 Cryogenic Pipe Support lng-pipe-support 3800× 3,800 · part
3.9 Flange Bolt Set Item lng-flange-bolt 17000× 17,000 · part
4 Dual-Fuel Propulsion Plant 10 parts lng-propulsion 1× 1 12,740 assembly
4.1 Dual-Fuel Two-Stroke Engine 9 parts lng-main-engine 2× 2 3,768 assembly
4.1.1 Cylinder Unit 9 parts + deeper › lng-cylinder-unit 5× 10 13 assembly
4.1.2 Engine Bedplate lng-engine-bedplate 1× 2 · part
4.1.3 Crankshaft lng-crankshaft 1× 2 · part
4.1.4 Engine Tie Rod lng-engine-tie-rod 60× 120 · part
4.1.5 Main Bearing Shell lng-main-bearing 6× 12 · part
4.1.6 Turbocharger lng-turbocharger 2× 4 · part
4.1.7 Engine Service Pump 5 parts + deeper › lng-engine-pump 4× 8 7 assembly
4.1.8 Fuel Injection Pump lng-fuel-injection-pump 5× 10 · part
4.1.9 Engine Pipe Bundle 4 parts + deeper › lng-engine-pipe-bundle 1× 2 3,600 assembly
4.2 Fixed-Pitch Propeller lng-propeller 2× 2 · part
4.3 Propeller Shaft Section lng-shaft-section 6× 6 · part
4.4 High-Pressure LNG Pump lng-hp-pump 3× 3 · part
4.5 Gas Valve Unit lng-gas-valve-unit 2× 2 · part
4.6 Gas Combustion Unit lng-gcu 1× 1 · part
4.7 Cryogenic Valve lng-cryo-valve 340× 340 · part
4.8 Pipe Spool lng-pipe-spool 650× 650 · part
4.9 Cryogenic Pipe Support lng-pipe-support 900× 900 · part
4.10 Flange Bolt Set Item lng-flange-bolt 3300× 3,300 · part
5 Deckhouse & Accommodation 4 parts lng-deckhouse 1× 1 35,959 assembly
5.1 Cabin Module 3 parts lng-cabin-module 38× 38 183 assembly
5.1.1 Joiner Panel lng-joiner-panel 22× 836 · part
5.1.2 Cabin Fitting lng-cabin-fitting 160× 6,080 · part
5.1.3 Cabin Door lng-cabin-door 1× 38 · part
5.2 Bridge Console lng-bridge-console 1× 1 · part
5.3 HVAC Air Handler lng-hvac-unit 4× 4 · part
5.4 Joiner Screw / Pin lng-joiner-screw 29000× 29,000 · part
6 Electrical System 6 parts lng-electrical 1× 1 57,820 assembly
6.1 Cable Run lng-cable-run 17000× 17,000 · part
6.2 Connector connector 9000× 9,000 · part
6.3 Cable Cleat lng-cable-cleat 26000× 26,000 · part
6.4 Main Switchboard lng-switchboard 4× 4 · part
6.5 Dual-Fuel Generator Set 5 parts lng-genset 4× 4 754 assembly
6.5.1 Genset Power Assembly 6 parts + deeper › lng-genset-cylinder 9× 36 6 assembly
6.5.2 Alternator lng-alternator 1× 4 · part
6.5.3 Turbocharger lng-turbocharger 1× 4 · part
6.5.4 Engine Service Pump 5 parts + deeper › lng-engine-pump 3× 12 7 assembly
6.5.5 Genset Skid & Exhaust 4 parts + deeper › lng-genset-skid 1× 4 677 assembly
6.6 Light Fixture lng-light-fixture 2800× 2,800 · part
7 Ballast & Machinery Piping 5 parts lng-ballast-piping 1× 1 34,403 assembly
7.1 Ballast Pump lng-ballast-pump 3× 3 · part
7.2 Pipe Spool lng-pipe-spool 6000× 6,000 · part
7.3 Pipe Flange lng-pipe-flange 9000× 9,000 · part
7.4 Flange Bolt Set Item lng-flange-bolt 18000× 18,000 · part
7.5 Ballast/Service Valve lng-ballast-valve 1400× 1,400 · part
8 Deck Machinery & Lifesaving 8 parts lng-deck-machinery 1× 1 5,828 assembly
8.1 Mooring Winch 6 parts lng-mooring-winch 6× 6 10 assembly
8.1.1 Winch Drum lng-winch-drum 2× 12 · part
8.1.2 Winch Gearbox lng-winch-gearbox 1× 6 · part
8.1.3 Hydraulic Motor lng-hydraulic-motor 1× 6 · part
8.1.4 Winch Brake lng-winch-brake 1× 6 · part
8.1.5 Ball Bearing ball-bearing 4× 24 · part
8.1.6 Fastener Set fastener-set 1× 6 · part
8.2 Anchor & Chain Set 3 parts lng-anchor-set 1× 1 1,104 assembly
8.2.1 Bower Anchor lng-anchor 2× 2 · part
8.2.2 Chain Cable Link lng-chain-link 1100× 1,100 · part
8.2.3 Chain Stopper lng-chain-stopper 2× 2 · part
8.3 Mooring Fitting lng-mooring-fitting 60× 60 · part
8.4 Enclosed Lifeboat lng-lifeboat 2× 2 · part
8.5 Inflatable Liferaft lng-liferaft 8× 8 · part
8.6 Deck Crane 5 parts lng-deck-crane 2× 2 127 assembly
8.6.1 Crane Boom & Pedestal lng-crane-boom 1× 2 · part
8.6.2 Hydraulic Motor lng-hydraulic-motor 2× 4 · part
8.6.3 Hydraulic Power Unit 5 parts + deeper › lng-hydraulic-power-unit 1× 2 122 assembly
8.6.4 Winch Drum lng-winch-drum 1× 2 · part
8.6.5 Fastener Set fastener-set 1× 2 · part
8.7 Equipment Foundation lng-deck-foundation 140× 140 · part
8.8 Flange Bolt Set Item lng-flange-bolt 4200× 4,200 · part

Something wrong in this list? Report a problem with this BOM.

Sourcing: possible vendors

Browse the supplier directory → Prices, MOQ, and lead times are algorithmic estimates, not quotes, and not claims about these companies. Company mappings are curated by keyword; est. price band $2k–$500M. How estimates work
VendorHQSpecialtyMOQLead time
🇰🇷HD Hyundai
hd.com ↗
Ulsan, KR Shipbuilder made to order 52–104 wks
🇮🇹Fincantieri
fincantieri.com ↗
Trieste, IT Shipbuilder made to order 52–104 wks
damen.com ↗ Gorinchem, NL Shipbuilder made to order 52–104 wks
🇺🇸Brunswick
brunswick.com ↗
Mettawa, US Marine & boats made to order 52–104 wks
🇨🇳CSSC
cssc.net.cn ↗
Shanghai, CN Shipbuilding conglomerate made to order 52–104 wks

925-word article